FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-04-29.q944 Dumps
  • ««
  • «
  • …
  • 88
  • 89
  • 90
  • 91
  • 92
  • 93
  • 94
  • 95
  • 96
  • 97
  • …
  • »
  • »»
Download Now

Question 456

You are the project manager of GHT project. You have initiated the project and conducted the feasibility study. What result would you get after conducting feasibility study?
Each correct answer represents a complete solution. (Choose two.)

Correct Answer: A,D
Explanation/Reference:
Explanation:
The completed feasibility study results should include a cost/benefit analysis report that:
Provides the results of criteria analyzed (e.g., costs, benefits, risk, resources required and

organizational impact)
Recommends one of the alternatives and a course of action

Incorrect Answers:
B, C: Project management plan and risk response plan are the results of plan project management and plan risk response, respectively. They are not the result of feasibility study.
insert code

Question 457

Which of the following BEST provides an early warning that network access of terminated employees is not being revoked in accordance with the service level agreement (SLA)?

Correct Answer: A
Section: Volume D
insert code

Question 458

An application runs a scheduled job that compiles financial data from multiple business systems and updates the financial reporting system. If this job runs too long, it can delay financial reporting. Which of the following is the risk practitioner's BEST recommendation?

Correct Answer: B
insert code

Question 459

What is the most important benefit of classifying information assets?

Correct Answer: D,E
B, and A are incorrect. These all are less significant than identifying controls.
insert code

Question 460

Which of the following is an acceptable method for handling positive project risk?

Correct Answer: A
Section: Volume B
Explanation:
Exploit is a method for handling positive project risk.
Incorrect Answers:
B, C, D: These are all responses which is used for negative risks, and not the positive risk.
insert code
  • ««
  • «
  • …
  • 88
  • 89
  • 90
  • 91
  • 92
  • 93
  • 94
  • 95
  • 96
  • 97
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-04-29.q944 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.