FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-04-29.q944 Dumps
  • ««
  • «
  • …
  • 90
  • 91
  • 92
  • 93
  • 94
  • 95
  • 96
  • 97
  • 98
  • 99
  • …
  • »
  • »»
Download Now

Question 466

You are preparing to complete the quantitative risk analysis process with your project team and several subject matter experts. You gather the necessary inputs including the project's cost management plan.
Why is it necessary to include the project's cost management plan in the preparation for the quantitative risk analysis process?

Correct Answer: A
Explanation/Reference:
Explanation:
The cost management plan is an input to the quantitative risk analysis process because of the cost management control it provides.
The cost management plan sets how the costs on a project are managed during the project's life cycle. It defines the format and principles by which the project costs are measured, reported, and controlled. The cost management plan identifies the person responsible for managing costs, those who have the authority to approve changes to the project or its budget, and how cost performance is quantitatively calculated and reported upon.
Incorrect Answers:
B: The cost management plan defines the estimating, budgeting, and control of the project's cost.
C: While the cost management plan does define the cost change control system, this is not the best answer for this D: This is not a valid statement. The cost management plan is an input to the quantitative risk analysis process.
insert code

Question 467

You are the project manager of GHT project. You have implemented an automated tool to analyze and report on access control logs based on severity. This tool generates excessively large amounts of results. You perform a risk assessment and decide to configure the monitoring tool to report only when the alerts are marked "critical". What you should do in order to fulfill that?

Correct Answer: B
C, and D are incorrect. These options are not relevant to the change of sensitivity of the monitoring tools.
insert code

Question 468

You are the project manager for BlueWell Inc. You have noticed that the risk level in your project increases above the risk tolerance level of your enterprise. You have applied several risk responses. Now you have to update the risk register in accordance to risk response process. All of the following are included in the risk register except for which item?

Correct Answer: C
Explanation/Reference:
Explanation:
The risk register does not examine the network diagram and the critical path. There may be risks associated with the activities on the network diagram, but it does not address the network diagram directly.
The risk register is updated at the end of the plan risk response process with the information that was discovered during the process. The response plans are recorded in the risk register. In the risk register, risk is stated in order of priority, i.e., those with the highest potential for threat or opportunity first. Some risks might not require response plans at all, but then too they should be put on a watch list and monitored throughout the project. Following elements should appear in the risk register:
List of identified risks, including their descriptions, root causes, and how the risks impact the project

objectives
Risk owners and their responsibility

Outputs from the Perform Qualitative Analysis process

Agreed-upon response strategies

Risk triggers

Cost and schedule activities needed to implement risk responses

Contingency plans

Fallback plans, which are risk response plans that are executed when the initial risk response plan

proves to be ineffective
Contingency reserves

Residual risk, which is a leftover risk that remains after the risk response strategy has been

implemented
Secondary risks, which are risks that come about as a result of implementing a risk response
insert code

Question 469

Which of the following parameters would affect the prioritization of the risk responses and development of the risk response plan? Each correct answer represents a complete solution. Choose three.

Correct Answer: A,C,D
Explanation/Reference:
Explanation:
The prioritization of the risk responses and development of the risk response plan is influenced by several parameters:
Cost of the response to reduce risk within tolerance levels

Importance of the risk

Capability to implement the response

Effectiveness of the response

Efficiency of the response

Incorrect Answers:
B: Time required to mitigate risk does not influence the prioritization of the risk and development of the risk response plan. It affects the scheduled time of the project.
insert code

Question 470

Which of the following attributes of a key risk indicator (KRI) is MOST important?

Correct Answer: D
insert code
  • ««
  • «
  • …
  • 90
  • 91
  • 92
  • 93
  • 94
  • 95
  • 96
  • 97
  • 98
  • 99
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-04-29.q944 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.