FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-04-29.q944 Dumps
  • ««
  • «
  • …
  • 93
  • 94
  • 95
  • 96
  • 97
  • 98
  • 99
  • 100
  • 101
  • 102
  • …
  • »
  • »»
Download Now

Question 481

You work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the project's key stakeholders to help you identify and communicate the identified risk events. You will also need several documents to help you and the stakeholders identify the risk events. Which one of the following is NOT a document that will help you identify and communicate risks within the project?

Correct Answer: D,E
B, and A are incorrect. These are an input to risk identification.
Identify Risks is the process of determining which risks may affect the project. It also documents
risks' characteristics. The Identify Risks process is part of the Project RiskManagement knowledge
area. As new risks may evolve or become known as the project progresses through its life cycle,
Identify Risks is an iterative process. The process should involve the project team so that they can
develop and maintain a sense of ownership and responsibility for the risks and associated risk
response actions. Risk Register is the only output of this process.
insert code

Question 482

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You have completed identifying all possible risks along with the stakeholders and team and have calculated the probability and impact of these risks. Which of the following would you need next to help you prioritize the risks?

Correct Answer: B
Section: Volume A
Explanation:
Risk rating rules define how to prioritize risks after the related probability and impact values are calculated.
These are generally included in the organizational process assets and are refined for individual projects.
Incorrect Answers:
A: Affinity Diagram is a method of group creativity technique to collect requirements which allows large numbers of ideas to be sorted into groups for review and analysis. This is generally used in Scope Management and not applicable to this option.
C: A Project Network diagram shows the sequencing and linkage between various project tasks and is not applicable to this question D: Risk categories are an output of the Perform Qualitative Risk Analysis process and not a tool to complete the process.
insert code

Question 483

Which of the following BEST confirms the existence and operating effectiveness of information systems controls?

Correct Answer: A
insert code

Question 484

Which of the following is MOST important to understand when determining an appropriate risk assessment approach?

Correct Answer: D
insert code

Question 485

Which of the following are the principles of risk management?
Each correct answer represents a complete solution. Choose three.

Correct Answer: A,B,D
The International Organization for Standardization (ISO) identifies the following principles of risk management. Risk management should: create value be an integral part of organizational processes be part of decision making explicitly address uncertainty be systematic and structured be based on the best available information be tailored take into account human factors be transparent and inclusive be dynamic, iterative, and responsive to change be capable of continual improvement and enhancement
insert code
  • ««
  • «
  • …
  • 93
  • 94
  • 95
  • 96
  • 97
  • 98
  • 99
  • 100
  • 101
  • 102
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-04-29.q944 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.