FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. ISACA Certification
  3. CRISC Exam
  4. ISACA.CRISC.v2022-10-16.q179 Dumps
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • …
  • »
  • »»
Download Now

Question 81

Which of the following is MOST important when developing key performance indicators (KPIs)?

Correct Answer: D
Explanation/Reference:
Explanation:
Monitor and analyze key performance indicators (KPIs) to identify changes or trends related to the control environment and determine the efficiency and effectiveness of controls.
Reference: https://m.isaca.org/Certification/Additional-Resources/Documents/CRISC-Item-Development- Guide_bro_Eng_0117.pdf
insert code

Question 82

Which of the following is the GREATEST risk associated with an environment that lacks documentation of the architecture?

Correct Answer: D
insert code

Question 83

You are preparing to complete the quantitative risk analysis process with your project team and several subject matter experts. You gather the necessary inputs including the project's cost management plan. Why is it necessary to include the project's cost management plan in the preparation for the quantitative risk analysis process?

Correct Answer: A
is incorrect. This is not a valid statement. The cost management plan is an input to the quantitative risk analysis process. Answer:B is incorrect. The cost management plan defines the estimating, budgeting, and control of the project's cost. Answer:C is incorrect. While the cost management plan does define the cost change control system, this is not the best answer for this
insert code

Question 84

Which of the following BEST provides an early warning that network access of terminated employees is not being revoked in accordance with the service level agreement (SLA)?

Correct Answer: A
insert code

Question 85

The best way to test the operational effectiveness of a data backup procedure is to:

Correct Answer: C
Section: Volume D
Explanation/Reference:
insert code
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download ISACA.CRISC.v2022-10-16.q179 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.