Which of the following is an output of the Perform Integrated Change Control process?
Correct Answer: D
Question 64
Match each dimension of the communications management plan to its corresponding focus.
Correct Answer:
Question 65
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
Correct Answer: D
Section: Volume D Explanation: Process: 9.3 Develop Project Team Definition: The process of improving competencies, team member interaction, and overall team environment to enhance project performance. The key benefit of this process is that it results in improved teamwork, enhanced people skills and competencies, motivated employees, reduced staff turnover rates, and improved overall project performance. Key Benefit: The key benefit of this process is that it results in improved teamwork, enhanced people skills and competencies, motivated employees, reduced staff turnover rates, and improved overall project performance. Inputs 1. Human resource management plan 2. Project staff assignments 3. Resource calendars Tools & Techniques 1. Interpersonal skills 2. Training 3. Team-building activities 4. Ground rules 5. Colocation 6. Recognition and rewards 7. Personnel assessment tools Outputs 1. Team performance assessments 2. Enterprise environmental factors updates