A well-established PMO in the banking sector has decided to evolve the company's current project management practices as an element of its mandate to drive organizational project management maturity.
However, the proposed changes were received with skepticism by the leadership team due to concerns about the impact on delivery throughput. The PMO professional was asked to address these concerns.
How should the PMO professional begin to address this issue?
The board of directors wants to oversee the company's strategic portfolio of capital projects. The PMO will support portfolio management.
What should the PMO professional do to ensure that the portfolio's alignment to strategy meets executives' expectations?
A software company hired a PMO professional to establish a new PMO to oversee the performance of its projects and create the required processes. The new PMO professional immediately conducted project management training sessions for all project managers, developed project templates, and regularly conducted project audits. After the PMO had been in service for a year, senior management decided to shut down the PMO due to lack of value generation.
What should the PMO professional have done differently to ensure that the PMO generated the desired value?
A PMO professional is tasked with ensuring the organization's competency framework stays relevant to evolving industry trends and internal strategic needs. Which approach should the PMO professional take to achieve this?
Due to a recent organizational transformation, the PMO has been excluded from strategic meetings and discussions. Although still responsible for program and project performance reporting, business representatives are now bypassing the PMO and directly approaching project managers for specific performance updates.
What actions should the PMO professional take to ensure the PMO remains valued by the organization?