The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.
What should the project manager do regarding those risks?
The risk manager organizes a stakeholder meeting to obtain agreement on project risk response strategies. At the conclusion of this meeting, the risk response strategies should be which of the following?
The risk manager for a project successfully establishes the risk management plan, the risk register and performs the qualitative risk analysis with the team. As the first step of the analysis, the risk manager develops the probability and impact scales. The scales are presented to the project manager, who refuses to accept the proposed scales.
What did the risk manager overlook prior to developing probability and impact scales?
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?
The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?