FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • IBM
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • IBM
    IBM
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMI-RMP Exam
  4. PMI.PMI-RMP.v2024-07-20.q130 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 11

A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.
How should the risk manager interpret such a low CPI value?

Correct Answer: B
Explanation
A low CPI value (0.53) indicates that the project is over budget. This may be due to an inaccurate cost baseline, which means the initial budget estimation was not correct. This would not necessarily mean that cost control processes are ineffective, actual reported costs are inaccurate, or cost-related risks are effectively managed.
The CPI value is calculated by dividing the earned value (EV) by the actual cost (AC). A CPI value of less than 1 indicates that the project is over budget, meaning that the actual cost is higher than the planned cost. A low CPI value can have several possible causes, such as poor estimation, scope creep, change requests, or inaccurate reporting. However, in this case, the SPI value is greater than 1, which indicates that the project is ahead of schedule, meaning that the earned value is higher than the planned value. This suggests that the cost baseline, which is derived from the planned value, is inaccurate and does not reflect the true cost of the work. Therefore, the risk manager should interpret such a low CPI value as a sign of an inaccurate cost baseline, and not as a result of ineffective cost control processes, inaccurate actual costs, or effective cost related risk management. References: PMI-RMP Certification Handbook1, page 9; PMBOK Guide, page
267.
insert code

Question 12

You are the project manager of the GGK project for your company. The GGK project has a budget of
$1,265,100 and is currently 40 percent complete. In this project, you elected to add labor to the project to increase the likelihood of completing the project early as the project was only scheduled to be 35 percent complete at this time. This positive risk response, while keeping the project ahead of schedule, has added significant costs to the project. You have already spent $575,000 to reach this point in the project.
Management would like to know what your cost performance index and the schedule performance index is for this project. What are these values?

Correct Answer: B
insert code

Question 13

You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can depict the resources that will be used within the project. Which of the following diagrams will you create to accomplish the task?

Correct Answer: C
insert code

Question 14

A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?

Correct Answer: B
Explanation
The risk manager should use the Delphi method in this situation, as this is a technique that can help resolve differences among experts and reach a consensus on the identified risks and their characteristics. The Delphi method is a tool used to make quick decisions with consensus. This technique consists of sending several sets of anonymous questions to each expert. This is followed by a group discussion after every round. The Delphi method can help the risk manager to solicit the opinions of all experts without revealing their identities. This way, the experts can express their views freely and honestly, without being influenced or intimidated by others. The Delphi method can also reduce personal bias, ego, or emotional conflict among the participants.
The risk manager can use the results of the Delphi method to create a list of potential risks and their causes, effects, and probabilities. The other options are not appropriate techniques for the risk manager to use in this situation. Brainstorming is a technique that can help generate ideas and identify risks, but it may not be effective in resolving differences among experts, as it involves open and spontaneous discussion. Focus group is a technique that can help collect requirements and opinions from stakeholders, but it may not be suitable for resolving technical disagreements among experts, as it involves a moderated and structured discussion.
Checklist analysis is a technique that can help identify risks based on historical information and lessons learned, but it may not be helpful in resolving differences among experts, as it involves a predefined list of potential risks. References: 3, 4, 5
insert code

Question 15

Joyce is the project manager for her company. Joyce and her project team are working through the quantitative analysis for certain risk events within her project. According to the enterprise environmental factors the project manager is to perform sensitivity analysis on any risk with an impact greater than $5,000 in the project. What is the sensitivity analysis?

Correct Answer: B
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMI-RMP.v2024-07-20.q130 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.