FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • IBM
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • IBM
    IBM
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP-CN Exam
  4. PMI.PMP-CN.v2024-04-19.q212 Dumps
  • ««
  • «
  • …
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • …
  • »
  • »»
Download Now

Question 66

一個項目正在進行第五次迭代。由於經濟突然下滑,該公司收入大幅減少。策略方向是立即實施成本削減措施。
專案經理接下來該做什麼?

Correct Answer: A
Explanation
The project manager should schedule a meeting with the product owner, discuss priorities, and decide if anything from the backlog can be eliminated, based on current constraints, due to the sudden slump in the economy and the need to implement cost-reduction measures. This way, the project manager can align the project scope and deliverables with the changed business environment and stakeholder expectations, while minimizing the impact on the project valueand quality. The project manager can also use agile techniques, such as MoSCoW prioritization, to determine what features are must-haves, should-haves, could-haves, and won't-haves for the project. The project manager should not continue the current sprint without interruption, allow the project team to decide on the best path forward, or meet with the sponsor for guidance, as these options may not address the urgency and importance of the situation and may lead to wasted resources, misaligned goals, or delayed decisions. References: PMBOK Guide, 6th edition, page 177, Top 60+ PMP Exam Questions and Answers for 2023 - KnowledgeHut
insert code

Question 67

一名新專案經理被指派負責兩週前開始的正在進行的敏捷創新專案。在審查專案後,新專案經理發現前專案經理正計劃使用預測方法。前專案經理計劃在 8 個月內專案完全完成時向客戶展示第一個主要交付成果。
新的專案經理該做什麼?

Correct Answer: A
Explanation
According to the PMBOK Guide, 6th edition, an agile innovation project is a project that uses an agile approach to deliver innovative products, services, or results that meet the changing needs and expectations of the customers and stakeholders. An agile approach is a way of managing a project that delivers value in short iterations, encourages collaboration and feedback, and embraces change and uncertainty. A predictive approach is a way of managing a project that follows a detailed plan, defines the scope and requirements upfront, and minimizes changes and risks. In this question, the new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. The new project manager discovered that the previous project manager was planning to use a predictive approach, which is not suitable for an agile innovation project. The previous project manager also planned to present the first major deliverable to the client when the project was completely finished in 8 months, which is not consistent with the agile principle of delivering value early and often. The question asks what the new project manager should do in this situation.
Based on this information, the best answer is option A, which is to meet with the team to review the backlog and create small iterations that can deliver incremental value to the client. This is because meeting with the team to review the backlog and create small iterations is an agile practice that can help the new project manager to align the project with the agile approach and the customer needs. The backlog is a list of features, functions, requirements, enhancements, and fixes that deliver value to the customer. The iterations are fixed time periods, usually between one and four weeks, in which the team completes a set of backlog items and produces a potentially releasable product increment. Meeting with the team to review the backlog and create small iterations can help the new project manager to understand the project vision, scope, and priorities, as well as to plan and execute the project work in an agile manner. Meeting with the team to review the backlog and create small iterations can also help the new project manager to deliver incremental value to the client, as well as to obtain feedback and validation from the client and other stakeholders.
Option B, which is to continue working with the predictive approach to deliver the value at the end of the project, is not a good answer. This is because continuing working with the predictive approach may not be effective or efficient for an agile innovation project, as it may not be able to cope with the changing needs and expectations of the customer and stakeholders. Continuing working with the predictive approach may also result in delivering a product that does not meet the customer requirements or satisfaction, as well as wasting time and resources on unnecessary or irrelevant features or functions.Continuing working with the predictive approach may also contradict the agile values and principles, such as responding to change over following a plan, and delivering working software frequently.
Option C, which is to use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project, is not a good answer. This is because using a hybrid approach may not be appropriate or beneficial for an agile innovation project, as it may not fully leverage the advantages of the agile approach, such as delivering value early and often, and obtaining feedback and validation from the customer and stakeholders. Using a hybrid approach may also create confusion and inconsistency among the project team, the customer, and other stakeholders, as they may have different expectations and perceptions of the project scope, schedule, quality, and risks. Using a hybrid approach may also compromise the agile values and principles, such as satisfying the customer through early and continuous delivery of valuable software, and collaborating with the customer throughout the project.
Option D, which is to submit a change request to the project board to adjust the delivery date to 2 months earlier than planned, is not a good answer. This is because submitting a change request to the project board may not be necessary or effective for an agile innovation project, as it may not address the root cause of the problem, which is the mismatch between the project approach and the project type. Submitting a change request to the project board may also introduce additional risks and challenges to the project, such as scope creep, quality issues, stakeholder resistance, and team burnout. Submitting a change request to the project board may also violate the agile values and principles, such as welcoming changing requirements, and delivering working software frequently. References: PMBOK Guide, 6th edition, Chapter 1: Introduction1; Chapter 4: Project Integration Management2; Chapter 5: Project Scope Management3; PMI, 2023, PMP Exam Content Outline, Domain II: Process, Task 1: Execute project with the urgency required to deliver business value.
insert code

Question 68

在地理分散的團隊中,開發人員不斷延遲編碼活動。此活動處於關鍵路徑上。項目經理髮現,延誤的原因是開發人員對異地團隊共享的客戶需求缺乏了解。
項目經理應該做什麼?

Correct Answer: B
insert code

Question 69

一個團隊正在使用混合方法進行一個項目,他們面臨著來自一些利益相關者的許多障礙和阻礙。專案經理應該怎麼做才能提升專案績效?

Correct Answer: B
Explanation
= The project manager should address and remove obstacles and blockers for the team to improve project performance. Obstacles and blockers are anything that prevents the team from completing their work or delivering value to the customer. They can be internal or external, technical or non-technical, predictable or unpredictable. The project manager should identify, prioritize, and resolve them as soon as possible, by using effective communication, negotiation, and problem-solving skills. The project manager should also protect the team from unnecessary distractions and interruptions, and provide them with the necessary resources and support. Empowering the team members, asking stakeholders to communicate directly, or adding blockers to the issue log and risk management plan are not the best actions to take, as they may not address the root cause or the urgency of the obstacles and blockers, or they may create more confusion or conflict. References:
PMBOK Guide 7th Edition, Chapter 7: Team Performance, Section 7.2: Enable Team Performance, Page 181 PMBOK Guide 6th Edition, Chapter 9: Resource Management, Section 9.4: Manage Team, Page 341 Agile Practice Guide, Chapter 3: Implementing Agile: Creating an Agile Environment, Section 3.4:
Delivery Practices, Page 40
insert code

Question 70

客戶發起了較小的範圍變更,並希望在沒有延遲或額外成本的情況下完成此變更。項目經理認為他們有足夠的授權自行做出決定,但不太確定。
項目經理接下來應該做什麼?

Correct Answer: D
insert code
  • ««
  • «
  • …
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMP-CN.v2024-04-19.q212 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.