FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP-CN Exam
  4. PMI.PMP-CN.v2024-04-19.q212 Dumps
  • ««
  • «
  • …
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • …
  • »
  • »»
Download Now

Question 76

一個專案團隊被要求恢復一個由於環境和條件快速變化而暫停了幾個月的專案的開發活動。專案負責人該做什麼?

Correct Answer: A
Explanation
= This answer is based on the agile practice of backlog refinement, which is the process of reviewing, updating, and prioritizing the backlog items with the project team and other stakeholders. By reviewing the items remaining in the backlog with the project team, the project lead can ensure that the team has a clear and shared understanding of the project scope, requirements, and value. This will also help to identify and address any changes, dependencies, risks, or issues that may have occurred during the suspension of the project. This approach will enable the project team to resume the development activities with confidence and alignment. References: (Project Management Professional (PMP) Reference Materials source and documents) A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter
14: Enabling Change, Section 14.2: Leading the Team, page 334.
Agile Practice Guide, Chapter 3: Life Cycle Selection, Section 3.3: Implementing Agile: Creating an Agile Environment, page 32.
insert code

Question 77

一位敏捷協調員為一個新項目召集了一個團隊。該團隊和協調員尚未一起參與過項目。
輔導員應該如何進行?

Correct Answer: C
insert code

Question 78

專案經理在專案執行階段遇到治理問題。一名團隊成員抱怨接受多人分配的任務,並表示他們無法有效運作。
專案經理首先應該在專案治理結構中建立什麼?

Correct Answer: C
Explanation
The project manager should establish a clear RACI matrix first in the project governance structure to address the governance issue during the project execution phase. According to the PMBOK Guide, a RACI matrix is a tool that defines the roles and responsibilities of project team members and other stakeholders for each project activity or deliverable[1]. A RACI matrix uses four categories to assign the level of involvement for each stakeholder: responsible, accountable, consult, and inform[1]. By creating a clear RACI matrix, the project manager can avoid role ambiguity and confusion, and ensure that each team member knows who to report to and who to communicate with for each project task. This way, the project manager can improve the team performance and satisfaction, and resolve the governance issue. The other options are not the first things that the project manager should establish in the project governance structure, as they do not directly address the root cause of the issue.
A risk management and issues resolution plan is a document that describes how the project will identify, analyze, respond to, and monitor risks and issues[1]. It does not define the roles and responsibilities of the project team members and other stakeholders.
A resource management and conflict resolution plan is a document that describes how the project will acquire, develop, manage, and release the human and physical resources needed for the project[1]. It also includes the methods and techniques for resolving conflicts among the project team members and other stakeholders[1]. It does not define the roles and responsibilities of the project team members and other stakeholders.
A clear project work breakdown structure (WBS) and timeline is a graphical representation of the project scope and schedule, showing the hierarchical decomposition of the project deliverables and activities, and the estimated duration and dependencies of each activity[1]. It does not define the roles and responsibilities of the project team members and other stakeholders.
insert code

Question 79

在實施過程中,為項目分配了新的項目經理。項目經理意識到,新的稅收政策可能會帶來成本超支 25% 的風險。項目經理更新了風險登記冊並保持項目正常運行。首席執行官宣布該項目可能被取消,因為可接受的成本超支僅為 20%。項目經理非常驚訝,因為這是新信息。
項目經理應該怎樣做才能避免這種情況?

Correct Answer: C
insert code

Question 80

專案經理正在領導一個他們過去曾合作過的全球團隊,並且與他們高度信任。團隊位於不同的國家和時區,需要及時做出決策。
為了確保專案在團隊中順利進行,專案經理應該如何進行授權?

Correct Answer: A
Explanation
According to the Project Management Professional (PMP) Reference Materials, a project manager should delegate certain authorities and share information to allow fair decision-making when leading a global team that they have worked with in the past and have a high level of trust with them. This is because the project manager needs to balance the need for autonomy and control in a global project environment. By delegating certain authorities, the project manager can empower the team members to make decisions that are appropriate for their local context and time zone, and avoid delays or conflicts due to centralized decision-making. By sharing information, the project manager can ensure that the team members have access to the relevant and accurate data and knowledge that they need to make informed decisions, and also foster transparency and collaboration among the team members. Sharing information can also help the project manager to monitor the progress and performance of the team, and provide feedback and guidance when needed. Delegating certain authorities and sharing information can help the project manager to leverage the trust and experience of the team, and enhance the efficiency and effectiveness of the project. References: Project Management Professional (PMP) Exam Content Outline, A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Global projects : how to manage them successfully - Project Teams,
[Leadership in Project Management: The Ultimate Guide].
insert code
  • ««
  • «
  • …
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMP-CN.v2024-04-19.q212 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.