Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
Which object is used to allocate the costs from a claim to the project structure?
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.