Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
Where can you assign the user status profile for WBS elements? Note: There are 3 correct Answers to this question.
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.