Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
What could be a reason to use expert mode in the valuation method for results analysis?
You are working with predefined project coding masks to create projects. Which of the following statements apply? Note: There are 2 correct Answers to this question.
Where do you control whether a project stock is managed as valuated or non-valuated project stock?