FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • IBM
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • IBM
    IBM
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. USGBC Certification
  3. LEED-AP-BD-C Exam
  4. USGBC.LEED-AP-BD-C.v2024-05-18.q93 Dumps
  • ««
  • «
  • …
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • …
  • »
  • »»
Download Now

Question 56

Which is a benefit of earning Regional Priority credits?

Correct Answer: A
Explanation
A benefit of earning Regional Priority credits is that the LEED project can achieve more sustainable outcomes by recognizing the issues that are a priority in the project's location. Regional Priority credits are not new LEED credits, but instead are existing credits that USGBC regional councils and chapters have designated as being particularly important for their areas1. The incentive to achieve the credits is in the form of a bonus point. If an RP base credit is earned, then a bonus point is awarded to the project's total points1. This way, the project can address the geographically specific environmental, social equity and public health priorities of its location2. References:
Regional priority credit lookup | U.S. Green Building Council
Regional Priority (RP) credits - U.S. Green Building Council
insert code

Question 57

Which of the following would be most useful to a school project that is attempting to pursue Water Efficiency Credit, Indoor Water Use Reduction?

Correct Answer: D
Explanation
The Water Efficiency Credit, Indoor Water Use Reduction aims to reduce indoor water consumption by installing water-efficient fixtures and fittings, such as faucets, showerheads, toilets, and urinals1. A commercial dishwasher that is ENERGY STAR labeled or performance equivalent would help reduce the water use for dishwashing, which is one of the process water uses included in the credit calculation2. A standard garbage disposal would not reduce water use, but rather increase it. An electronic submeter at the domestic water supply pipe to the building would help measure and monitor water use, but not directly reduce it. An open-loop HVAC system that discharges potable cooling water to a nearby lake would waste a lot of water and potentially harm the environment.
References:
* Indoor Water Use Reduction
* "Maximizing Water Efficiency in Commercial Buildings: Understanding LEED BD+C Water Efficiency Credits"
insert code

Question 58

Increasing which of the following variables will require an increase in the outdoor airflow rate under Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?

Correct Answer: B
Explanation
The outdoor airflow rate is the amount of outdoor air that is supplied to the building by the ventilation system to dilute indoor air pollutants and provide fresh air for the occupants. The outdoor airflow rate depends on the ventilation standard that the project follows, which can be either ASHRAE 62.1-2010 or CEN Standard EN
15251-20071. Both standards specify the minimum outdoor airflow rate per person and per unit area for different occupancy types and zones. Therefore, increasing the number of occupants will require an increase in the outdoor airflow rate to maintain the minimum ventilation level. The other variables, such as supply air velocity, system ventilation efficiency, and supply air temperature set point, do not directly affect the outdoor airflow rate, although they may influence the energy consumption and thermal comfort of the ventilation system.
References:
* LEED Reference Guide for Building Design and Construction v4
* Minimum Indoor Air Quality Performance
* Ventilation for Acceptable Indoor Air Quality - ASHRAE
* Indoor environmental input parameters for design and assessment of ... - CEN
insert code

Question 59

Which of the following is true regarding LEED Pilot Credits?

Correct Answer: D
Explanation
One of the requirements for attempting a pilot credit is to complete a feedback survey after submitting the project for review. The LEED v4 Reference Guide for Building Design and Construction states that "the project team must complete a feedback survey for each pilot credit attempted. The survey link is provided in the pilot credit language. The survey must be completed after the project has been submitted for review and before the project receives a final rating"1. The feedback survey is an important tool for USGBC to evaluate the effectiveness and applicability of the pilot credit, and to make improvements or modifications based on the project team's experience.
References:
*LEED v4 Reference Guide for Building Design and Construction, Innovation Credit: Pilot, page 7571
*Pilot credits and pilot alternative compliance paths (ACPs)2
insert code

Question 60

When preparing the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, the ConstructionGeneral Permit must contain which of the following?

Correct Answer: C
Explanation
The Construction General Permit (CGP) for the Sustainable Sites Prerequisite, Construction Activity Pollution Prevention, must contain an installation plan for perimeter control.This is part of the Erosion and Sedimentation Control (ESC) Plan, which is designed to prevent loss of soil during construction by stormwater runoff and/or wind erosion, prevent sedimentation of storm sewer or receiving streams, and prevent polluting the air with dust and particulate matter1.
References:
* Sustainable Sites Prerequisites | GlobalSpec
insert code
  • ««
  • «
  • …
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download USGBC.LEED-AP-BD-C.v2024-05-18.q93 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.