A downtown office building is unable to construct dedicated parking for its occupants. However, the building developer has partnered with a parking garage to offer discounted parking for its occupants. If the discounted parking rate is $450 per month, how much must the rate be for green vehicles for the building to receive one point for Location and Transportation Credit, Green Vehicles?
Correct Answer: A
Explanation For the building to receive one point for Location and Transportation Credit, Green Vehicles, the rate for green vehicles must be 80% less than the regular parking rate.Therefore, if the discounted parking rate is $450 per month, the rate for green vehicles must be $90 per month (20% of $450).References: LEED AP Building Design + Construction (LEED AP BD+C) V4 resources1
Question 37
When a project team sustainably develops a project site, the design should
Correct Answer: C
Explanation remediate sites already in decline When a project team sustainably develops a project site, the design should aim to remediate sites already in decline, such as brownfields, degraded lands, or abandoned properties. By doing so, the project can restore the environmental quality, ecological functions, and social value of the site, as well as reduce the pressure on undeveloped lands and natural habitats. LEED offers credits for projects that choose to locate on and remediate sites already in decline, such as the Sustainable Sites Credit, Site Assessment and the Sustainable Sites Credit, Brownfields Remediation1.
Question 38
Plug-in task lighting will be utilized in a LEED project at all workstations. The task lighting is not included in the installed lighting power calculations for Energy and Atmosphere Prerequisite, Minimum Energy Performance since
Correct Answer: C
Explanation Plug-in task lighting is considered as furniture and is not included in the installed lighting power calculations for Energy and Atmosphere Prerequisite, Minimum Energy Performance. It is also not required to comply with the lighting control requirements of ASHRAE 90.1-2010. However, it can be used to satisfy the individual control requirement of Indoor Environmental Quality Credit, Interior Lighting, Option 1. References: LEED v4 for Building Design and Construction, p. 361 LEED v4 for Building Design and Construction, p. 6012 ASHRAE 90.1-2010, Section 9.1.13
Question 39
Which approach will contribute to maintaining compliance with Sustainable Sites Credit, Rainwater Management?
Correct Answer: A
Explanation Installing a bioretention area is an example of a low-impact development (LID) practice that can reduce runoff volume and improve water quality by replicating the natural hydrology and water balance of the site.This approach will contribute to maintaining compliance with Sustainable Sites Credit, Rainwater Management, which requires designing the site to retain the runoff from the developed site for at least the 80th percentile of rainfall events1.References: * Credit: Rainwater management | U.S. Green Building Council * Achieving SSc Rainwater Management in LEED v4.1
Question 40
The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy andAtmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?
Correct Answer: D
Explanation According to the LEED v4: Building Design + Construction Guide, the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, requires the project to hire a Commissioning Authority (CxA) to oversee the commissioning process for the mechanical, electrical, plumbing, and renewable energy systems and assemblies. The CxA must have documented commissioning authority experience in at least two building projects, and must not be an employee of the design or construction firms, although they may be contracted through them.The CxA must report the results, findings, and recommendations directly to the owner1. One of the required responsibilities for the CxA to achieve the prerequisite is to verify installation and performance of the commissioned systems.This includes conducting siteobservations and spot-checking of equipment installation, performing functional performance testing of the systems, verifying system performance by reviewing testing and balancing reports, and preparing a summary commissioning report of the activities and results1. The other choices are not required responsibilities for the CxA to achieve the prerequisite, but they are additional responsibilities for the CxA to achieve the Energy and Atmosphere Credit, Enhanced Commissioning, which goes beyond the prerequisite by including more systems, more verification activities, and more documentation.These additional responsibilities are2: * Verify that training requirements are completed. This includes reviewing training plans, agendas, and materials, and verifying that the training delivery and documentation are completed and consistent with the owner's project requirements (OPR). * Develop systems manual for the commissioned systems. This includes compiling and reviewing the systems manual that provides the necessary information for operating and maintaining the commissioned systems. * Review contractor submittals for the commissioned systems. This includes reviewing the design intent and basis of design documentation, and providing feedback on the contractor submittals related to the commissioned systems, such as shop drawings, product data, and samples. References: LEED v4: Building Design + Construction Guide, Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, Requirements1; LEED v4: Building Design + Construction Guide, Energy and Atmosphere Credit, Enhanced Commissioning, Requirements2