FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. USGBC Certification
  3. LEED-AP-BD-C Exam
  4. USGBC.LEED-AP-BD-C.v2025-06-23.q228 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 1

A project team is using the whole building simulation model to quantify the percentage of energy savings for the project. Which of the following should remain the same for both the baseline building and the proposed building?

Correct Answer: A
Explanation
This option requires the project team to use the same building operating schedule and occupancy hours for both the baseline building and the proposed building in the whole building simulation model1. This option ensures that the energy savings are calculated based on the same level of building activity and occupancy, which are major factors that affect the energy performance of a building2.
References: = LEED v4: Building Design + Construction Guide, [Whole Building Energy Simulation - an overview | ScienceDirect Topics].
insert code

Question 2

Which of the following actions should be taken to ensure that project teams understand and prioritize the selection of materials compliant with the Materials and Resources Credit, Building Product Disclosure and Optimization?

Correct Answer: A
For LEED BD+C Materials and Resources (MR) Credit: Building Product Disclosure and Optimization
, teams must prioritize material selection based on environmental and sustainability attributes.
* Including material requirements in project specifications ensures that all contractors, suppliers, and stakeholders follow the necessary sustainability criteria.
* Selecting locally sourced materials (Option B) is beneficial, but it is not the primary focus of this credit.
* Whole-building life-cycle analysis (Option C) is related to a different LEED credit (MR Credit:
Whole-Building Life-Cycle Impact Reduction).
* Procuring materials directly from raw suppliers (Option D) is not a LEED requirement and does not ensure compliance with disclosure and optimization requirements.
Option A is the correct choice because defining sustainability criteria in specifications helps ensure LEED-compliant materials are used throughout the project.
(Source: Official LEED BD+C Reference Manual)
insert code

Question 3

The Sustainable Sites Credit, Heat Island Reduction takes into account both new and three-year aged Solar Reflectance Index (SRI) values for roofing material because

Correct Answer: B
Explanation
SRI generally decreases with age
The Solar Reflectance Index (SRI) is a measure of the ability of a surface to reflect solar heat, as shown by a small temperature rise. It is calculated using the values of solar reflectance and thermal emittance of the surface. The higher the SRI, the lower the heat island effect. However, SRI generally decreases with age due to factors such as weathering, dirt accumulation, and biological growth. Therefore, the Sustainable Sites Credit, Heat Island Reduction takes into account both new and three-year aged SRI values for roofing material to ensure that the material maintains a high level of reflectance over time.
References:
SpecTopics: Heat Island Reduction Credit and LEED V4/V4.1 - Carlisle SynTec1 Solar Reflectance Index Measurements - Surface Optics Corp.2
insert code

Question 4

Which of the following credit options can a project team attempt if a local, national, or international organization indicates that the neighborhood site of the project has a significant cultural value?

Correct Answer: B
Detailed
Projects located in areas with significant cultural value can attempt the Priority Designation option under LEED Location and Transportation credits. This designation rewards projects in high-priority locations, such as cultural heritage sites, promoting development that respects and preserves the historical and cultural significance of the area.
insert code

Question 5

Which of the following are control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan?

Correct Answer: A
Source control is one of the control measures recommended by the Sheet Metal and Air Conditioning National Contractors Association (SMACNA) for the Indoor Environmental Quality Credit, Construction Indoor Air Quality Management Plan. Source control means minimizing the generation and emission of indoor air pollutants from the construction activities and materials. Some examples of source control are1:
*Using low-emitting adhesives, sealants, paints, coatings, and flooring systems that comply with the VOC limits of the applicable LEED credit.
*Storing absorptive materials in a protected area and covering them with plastic sheeting to prevent moisture and mold growth.
*Scheduling the installation of finish materials after the completion of wet and dusty work, such as concrete pouring, drywall sanding, and painting.
*Isolating work areas where high levels of contaminants are generated or used, such as welding, cutting, grinding, and solvent cleaning, and providing adequate ventilation and exhaust.
*Prohibiting smoking, eating, and drinking in the work areas, and providing designated areas for these activities.
References:
*Construction indoor air quality management plan | U.S. Green Building Council1
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download USGBC.LEED-AP-BD-C.v2025-06-23.q228 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2025 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.