FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. USGBC Certification
  3. LEED-AP-BD-C Exam
  4. USGBC.LEED-AP-BD-C.v2025-06-23.q228 Dumps
  • ««
  • «
  • …
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34
  • 35
  • …
  • »
  • »»
Download Now

Question 146

What credit rewards customers who change their normal consumption patterns in response to the varying price of energy over time?

Correct Answer: A
The Energy and Atmosphere Credit, Demand Response rewards projects that participate in demand response programs that aim to reduce peak electricity demand and shift the load to off-peak periods. The LEED v4 Reference Guide for Building Design and Construction states that "the intent of this credit is to increase participation in demand response technologies and programs that make energy generation and distribution systems more efficient, increase grid reliability, and reduce greenhouse gas emissions"1. The project team must either implement a permanent demand response program or develop a plan to implement a program within a year of occupancy. The project team must also demonstrate that the building has the capability to reduce its peak electricity demand by at least 10% in response to demand response signals.
References:
* LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Credit:
Demand Response, page 2721
* Demand response | U.S. Green Building Council2
insert code

Question 147

Which of the following is required for a cooling tower or evaporative condenser in Water Efficiency Prerequisite, Indoor Water Use Reduction?

Correct Answer: D
Makeup water meters, conductivity controllers and overflow alarms
According to the Water Efficiency Prerequisite for Indoor Water Use Reduction, cooling towers and evaporative condensers must be equipped with makeup water meters, conductivity controllers and overflow alarms to reduce water consumption and prevent water waste. These devices help monitor and control the water quality, flow rate and level of the cooling system, and alert the operators of any malfunctions or leaks.
insert code

Question 148

Which of the following variables must be included in the calculations for Indoor Environmental Quality Credit, Quality Views?

Correct Answer: D
According to the LEED v4 Reference Guide for Building Design and Construction, the calculations for Quality Views must include the following variables: window size and configuration, glazing factor, window head height, distance of the window from the floor, permanent interior obstructions, and exterior obstructions.
Ceiling heights, building furniture, and movable partitions are not required to be included in the calculations.
insert code

Question 149

Based on the results of a six-hour waste stream study, the project team for a retail project plans to provide dedicated areas for four easily recyclable waste streams: cardboard, plastic, metal and paper. The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite, Storage and Collection of Recyclables?

Correct Answer: D
According to the LEED v4 Reference Guide for Building Design and Construction, the project team must conduct a waste stream audit to identify the top five recyclable waste streams generated by the building and its occupants. The audit must cover a representative time period of a minimum of 24 hours, and must account for variations in the type and quantity of waste generated by different building uses and operations. The project team must then provide dedicated areas for the collection and storage of these materials for recycling.
The project team must also provide dedicated areas for the collection and storage of batteries, mercury- containing lamps, and electronic waste, or demonstrate that a local program is in place to properly dispose of these materials.
insert code

Question 150

Several Materials and Resources credits give a bonus location valuation factor, which allows products extracted, manufactured and produced within 100 mi. (161 km) of the project to take double valuation in credit calculations. The intent of this bonus is

Correct Answer: C
Explanation
The bonus location valuation factor in several Materials and Resources credits under LEED AP BD+C V4 is intended to incentivize the purchase of products that support the local economy.Products extracted, manufactured, and produced within 100 miles (161 km) of the project are valued at 200% of their cost within the calculations1.This adds value to locally produced products and materials2.
References:
* LEED Quiz 8: Ch. 9 Materials & Resources Flashcards | Quizlet
* LEED 2009 vs. LEED v4: Regional Materials - LaForce, LLC
insert code
  • ««
  • «
  • …
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34
  • 35
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download USGBC.LEED-AP-BD-C.v2025-06-23.q228 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.