FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. EXIN Certification
  3. ASM Exam
  4. EXIN.ASM.v2023-08-14.q103 Dumps
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • »
Download Now

Question 91

The Metal Company delivers custom software to other businesses. They have recently transitioned a team to Scrum, because their customers would like to be more involved in the software creation. They have settled on two-week sprints to make sure they can make changes to the product often.
The Product Owner will be briefed by the customers and get some time in the customer s businesses to help them understand the businesses and their priorities.
However the customers do not want to come in tor too many demonstrations, because that would cost them time and therefore money as well. Each customer has a different number of demonstrations they are willing to attend.
How should a Scrum team work with these customers?

Correct Answer: A
insert code

Question 92

To ensure that there is no gap between the customer's expectation from the project, and the deliverables produced, the Scrum Master has to eliminate environmental obstructions that the team may face, that may affect the quality of the deliverables. To do so, apart from Quality Planning, the team has to ensure Quality Control, and Quality Assurance. Which of the following statements is true regarding Quality Assurance and Quality Control?

Correct Answer: B
:
Quality control refers to the execution of the planned quality activities by the Scrum Team in the process of creating deliverables that are potentially shippable. It also includes learning from each set of completed activities in order to achieve continuous improvement. Within the cross-functional team, it is important to have the skills necessary to perform quality control activities. During the Sprint Retrospect Meeting, team members discuss lessons learned. These lessons act as inputs into continuous improvement and contribute to the improvement of ongoing quality control.
Quality is required not only in products, but also in processes. Quality assurance refers to the evaluation of processes and standards that govern quality management in a project to ensure that they continue to be relevant. Quality assurance activities are carried out as part of the work. In fact, quality assurance is a significant factor of the definition of Done. The deliverable isn't complete if appropriate quality assurance has not been conducted. Often, quality assurance is demonstrated during the Sprint Review Meeting.
insert code

Question 93

You are working in a $50 million project to remove weeds from National monument areas. You are responsible for achieving maximum business value for the project, and represent the Voice of the Customer. What role do you play in this project?

Correct Answer: B
Explanation
The Product Owner is the person responsible for achieving maximum business value for the project. He or she is also responsible for articulating customer requirements and maintaining business justification for the project.
The Product Owner represents the Voice of the Customer.
insert code

Question 94

Maria is one of the Scrum Master for a rail-road reservation system program. She facilitates the Daily Standup Meetings to enable the Scrum Team to discuss issues faced by individual members, and seek solutions to motivate the team. Which of the following represents the mandatory outputs of Conduct Daily Standup process?

Correct Answer: A
insert code

Question 95

The Scrum Team along with the Scrum Master adopted the Fist of Five technique to arrive at accurate estimations for the prioritized User Stories. The results of the vote of each team member are as follows: three members: 2 fingers; four members: 3 fingers; and two members: 5 fingers. Which of the following options is in plurality?

Correct Answer: B
insert code
  • ««
  • «
  • …
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • »
[×]

Download PDF File

Enter your email address to download EXIN.ASM.v2023-08-14.q103 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.