Which of the following is NOT a Scrum Master's responsibility?
A Scrum team is using a bum-down chart to track their progress. During the sprint, the graph looks like this.
What is certain about this sprint?
The Product Owner informs the team that the release will be date-driven.
What kind of buffer for uncertainty is most important to use in this type of release?
You are the Scrum Master for a team that is working on a project for a chemical engineering company. During one of the Sprints, the Product Owner suggests changes to the Acceptance Criteria on the basis of new requirements by the stakeholders. Which of the following best describes the steps that should be taken next in this situation?