The requirements elicitation process requires that the business analyst and team prepare for the requirements elicitation activities. There are three specific inputs that the business analyst will need in preparing for the requirements elicitation. Which of the following is NOT one of the three inputs the business analyst will use as he prepares for requirements elicitation?
A company that specialized in manufacturing vending machines for books has been in business for 10 years. As the e-book and online retailing grow, the company perceived that a change is required to respond to the new emerging market forces. However, the change should focus on reusability as much as possible to reduce expenses. After analyzing the current state with the business subject matter experts, the business analyst (BA) proposed investing in a new business line of vending machines that sell pay per use mobile device phone fast charging stations.
Due to the urgency of this change, the BA was asked to finalize requirements elicitation in the shortest possible time.
The BA was able to complete requirements elicitation activities in a short period of time. Which type of elicitation approach did the BA use?
Company A is a nation-wide leader in commercial demolition. Having just celebrated its 100th year of operations, the company decided to begin doing work internationally. The current system used for reporting company finances is unable to keep pace with the potential demands of doing work in geographically dispersed locations. Therefore, the company decided to replace its client-based Profit & Loss (P&L) reporting system with a more robust, web-based system. This will ensure transparency across the organization and enable better decision making.
The business analyst (BA) at Company A has recently completed several rounds of elicitation to determine the requirements for the new, web-based system. Over 1250 requirements were elicited. An initial Requirements Traceability Matrix (RTM) has been drafted, and a subset of the RTM can be seen below:
The BA will create a Data Model to meet which requirement?
A business analyst (BA) is preparing for observation. A passive approach has been selected for establishing performance metrics. What should be identic for the next step?
Following a recent, successful deployment a business analyst (BA) has noticed that several of the requirements are candidates for reuse in multiple, upcoming change initiatives. Which type of requirement is a potential candidate for re-use?