FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMO-CP Exam
  4. PMI.PMO-CP.v2025-12-30.q54 Dumps
  • ««
  • «
  • …
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • »
Download Now

Question 36

What is the relationship between organizational maturity in project management and PMO maturity?

Correct Answer: C
Organizational maturity in project managementandPMO maturityare related but separate concepts.
Organizational maturity refers to the overall development of the organization's project management capabilities, including governance, processes, tools, and resources across all levels. In contrast, PMO maturity focuses specifically on the maturity of the Project Management Office and its ability to support and govern projects, programs, and portfolios effectively.
While organizational maturity provides a broader view of the entire company's project management capabilities, PMO maturity addresses how well the PMO functions in aligning its operations with strategic objectives. Both are complementary, and improving either one can positively influence the other.
insert code

Question 37

A PMO is evaluating its Return On Investment (ROI) to justify its value to stakeholders. The team debates which factors have the most direct impact on this calculation. What factors may directly influence the calculation of the PMO ROI?

Correct Answer: B
The ROI of a PMO is calculated by evaluating tangible contributions to organizational goals. This includes:
* Number of completed projects: Highlights the productivity of the PMO.
* Total budget: Assesses efficiency in managing financial resources.
* Contribution to goals: Measures alignment with strategic objectives, showing direct value.
Factors such as team satisfaction or maturity contribute to operational success but are not directly measurable in ROI calculations.
References:
* PMI's The Standard for Portfolio Management, 4th Edition - ROI as a measure of value delivery.
* PMBOK Guide, 7th Edition - Financial and value-oriented metrics for assessing project success.
insert code

Question 38

How many performance indicators should be used for each PMO function in each evaluation cycle?

Correct Answer: C
In the context of PMO (Project Management Office) functions, performance indicators serve as critical tools to measure the effectiveness and success of the PMO's activities. The best practice is to use two to four performance indicators per function during each evaluation cycle. This ensures that the evaluation is comprehensive enough to provide valuable insights without creating unnecessary bureaucracy or excessive control, which can hinder flexibility and innovation.
A balanced number of indicators allows organizations to monitor the essential aspects of each function while maintaining efficiency and adaptability. By focusing on 2-4 indicators, PMOs can achieve a manageable level of control without overwhelming the team with too much data or analysis, which can be counterproductive. This approach aligns with the principle of tailoring and agility in project management, where processes and metrics should be adapted to fit the context of the work, providing maximum benefit with the least effort.
This recommendation is derived from the PMBOK Guide and related frameworks like Ricardo Vargas' PMO methodologies, which emphasize focusing on value, minimizing waste, and maintaining a lean and effective governance structure.
insert code

Question 39

A highly mature PMO is being questioned by organizational leaders about its value, as some key stakeholders feel their needs are not being met despite the PMO's functions being very well performed. Is it possible for a mature PMO to not generate value?

Correct Answer: C
Maturity alone does not guarantee value. While a PMO may excel in delivering sophisticated functions, its effectiveness depends on alignment with stakeholder needs and organizational goals. Misalignment can lead to high-performing functions that fail to address actual priorities, reducing perceived value.
Reference:
PMI's Stakeholder Management Principles in the PMBOK Guide, 7th Edition.
Pulse of the Profession insights on aligning maturity with value delivery.
insert code

Question 40

During a PMO strategy meeting, the leadership team discusses the best model for their organization, debating between the Center of Excellence, a Strategic PMO, and an Agile PMO. What is the ideal type or model of PMO for an organization looking to maximize efficiency and alignment with its strategic goals?

Correct Answer: D
There is no universally "best" PMO model. The optimal type depends on organizational priorities, culture, and strategic goals. PMOs must adapt their structure and functions to address specific challenges and align with stakeholder expectations, balancing flexibility and consistency.
References:
* Designing Adaptive PMOs (PMI Thought Leadership Series).
* PMI's Pulse of the Profession on PMO adaptability and customization.
insert code
  • ««
  • «
  • …
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • »
[×]

Download PDF File

Enter your email address to download PMI.PMO-CP.v2025-12-30.q54 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.