FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Scrum Certification
  3. PSM-I Exam
  4. Scrum.PSM-I.v2026-09-19.q335 Dumps
  • ««
  • «
  • …
  • 56
  • 57
  • 58
  • 59
  • 60
  • 61
  • 62
  • 63
  • 64
  • 65
  • …
  • »
  • »»
Download Now

Question 296

Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:

Correct Answer: C
insert code

Question 297

The Product Owner must release eachIncrement to production.

Correct Answer: C
insert code

Question 298

Which of the following are roles on a Scrum Team? (Choose all that apply.)

Correct Answer: B,C,D
According to the Scrum Guide, the Scrum Team consists of three roles: the Scrum Master, who coaches and facilitates the team; the Product Owner, who manages and prioritizes the Product Backlog; and the Development Team, who delivers a potentially releasable Increment at the end of each Sprint. Users and customers are not roles on the Scrum Team, but they are stakeholders who may provide feedback and input to the product.
insert code

Question 299

The time-box for a Daily Scrum?

Correct Answer: B
The correct answer is B, because the time-box for a Daily Scrum is 15 minutes. The Scrum Guide states that
"the Daily Scrum is a 15-minute time-boxed event for the Development Team to synchronize activities and create a plan for the next 24 hours."
insert code

Question 300

Who can abnormally terminate a Sprint?

Correct Answer: C
insert code
  • ««
  • «
  • …
  • 56
  • 57
  • 58
  • 59
  • 60
  • 61
  • 62
  • 63
  • 64
  • 65
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download Scrum.PSM-I.v2026-09-19.q335 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.