FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Scrum Certification
  3. PSM-I Exam
  4. Scrum.PSM-I.v2026-09-19.q335 Dumps
  • ««
  • «
  • …
  • 58
  • 59
  • 60
  • 61
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • …
  • »
  • »»
Download Now

Question 306

Which two of the following are true about the Scrum Master role? (Choose the best two answers.)

Correct Answer: A,D
insert code

Question 307

Why should the Product Owner be present at the Daily Scrum?

Correct Answer: A
The correct answer is A, because the Product Owner does not need to be present at the Daily Scrum. The Scrum Guide states that "the Daily Scrum is a 15-minute time-boxed event for the Development Team to synchronize activities and create a plan for the next 24 hours. ... The structure of the meeting is set by the Development Team and can be conducted in different ways if it focuses on progress toward the Sprint Goal." Therefore, the Daily Scrum is an internal event for the Development Team, and the Product Owner can attend only if invited by the Development Team.
insert code

Question 308

True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.

Correct Answer: A
The answer is A. True. The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal. According to the Scrum Guide, the Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how)1. The Sprint Goal is the single objective for the Sprint, and it provides coherence and focus for the Scrum Team2. The Sprint Backlog is a plan by and for the Developers, and it is updated throughout the Sprint as more is learned2.
insert code

Question 309

Who is responsible for the sizing of Product Backlog items? (Choose the best answer)

Correct Answer: E
insert code

Question 310

You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product Select two conditions you should strive tor in this scenario. (Choose the best two answers)

Correct Answer: C,E
Short Explanation: According to the Scrum Guide 20201, the product has one Product Backlog, which is the single source of work undertaken by the Scrum Team. The Product Backlog is ordered by the Product Owner, who is accountable for maximizing the value of the product resulting from the work of the Scrum Team. There should be only one Product Owner per product, who may represent the desires of a committee in the Product Backlog, but those wanting to change a Product Backlog item's priority must address the Product Owner. Having multiple Product Owners or Product Backlogs would create confusion, inconsistency, and waste in the Scrum process.
insert code
  • ««
  • «
  • …
  • 58
  • 59
  • 60
  • 61
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download Scrum.PSM-I.v2026-09-19.q335 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.