FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Scrum Certification
  3. PSM-I Exam
  4. Scrum.PSM-I.v2026-09-19.q335 Dumps
  • ««
  • «
  • …
  • 59
  • 60
  • 61
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • 68
  • »
Download Now

Question 321

How does Definition of "Done" help the Scrum Team? Select three most applicable items.

Correct Answer: B,C,E
insert code

Question 322

When is implementation of a Product Backlog item considered complete?

Correct Answer: B
According to the Scrum Guide1, an Increment is a concrete stepping stone toward the Product Goal. Each Increment is additive to all prior Increments and thoroughly verified, ensuring that all Increments work together. In order to provide value, an Increment must be usable. Multiple Increments may be created within a Sprint. The sum of the Increments is presented at the Sprint Review thus supporting empiricism. However, an Increment may be delivered to stakeholders prior to the end of the Sprint. The Sprint Review should never be considered a gate to releasing value. Therefore, implementation of a Product Backlog item is considered complete when the item has no work remaining in order to be potentially released.
insert code

Question 323

What factor should be considered when establishing the Sprint length? (Choose the best answer)

Correct Answer: B
The best answer is B. The need for the team to learn based on doing work and measuring results. The Sprint length should be chosen based on the complexity and volatility of the product and the environment, as well as the team's capability and Definition of Done. The Sprint length should enable the team to deliver a usable Increment of value that meets the feedback needs of the stakeholders and the business. The Sprint length should also allow the team to inspect and adapt their work processes and practices based on the outcomes of the Sprint. The other options are not valid reasons for choosing the Sprint length. The organization's mandate, team formation, and release schedule should not dictate the Sprint length, but rather be aligned with it. The Scrum Team should have the autonomy to choose the Sprint length that best suits their product and context.
You can learn more about how to choose the right Sprint length from these sources: How Long A Sprint Should Be?, How to Choose the Right Sprint Length in Scrum, What is a Sprint?, Determining the Sprint Length, and Sprint Length: What's the Right Length?.
insert code

Question 324

In order to achieve the benefits of Scrum, it is important to enact the value of commitment. What two actions demonstrate the commitment of Scrum Team members? (Choose two.)

Correct Answer: B,C
insert code

Question 325

Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).

Correct Answer: A
insert code
  • ««
  • «
  • …
  • 59
  • 60
  • 61
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • 68
  • »
[×]

Download PDF File

Enter your email address to download Scrum.PSM-I.v2026-09-19.q335 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.