A difference of opinion on the outcome of an earlier project has created a
'them and us' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Delivery Plan?
Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation

Xan Insurance Company is a friendly company with no separate private offices for individual managers. Staff members prefer to wander around the office space and have one-to-one chats rather than use email or have lots of meetings.
What action should the Project Manager take when planning for effective communication throughout the Web project?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
At the beginning of Solution Development Timebox A, the Timebox is being planned in detail. Although Foundations was conducted at a high level, the Prioritised Requirements List was baselined. Now the Solution Development Team is setting detailed acceptance criteria against each requirement.
Is this an appropriate approach to setting detailed acceptance criteria?