Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co- ordinating the project.
* The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.

The Customer Services Manager used to work in a call center, answering customer calls. Concerned for staff wellness, this manager has decided to invite anyone who is finding the changes overwhelming to contact them directly so that they can arrange appropriate support.
Which preference does this behavior BEST display?
Which 2 actions should the Workshop Facilitator take when preparing for the workshop?
Sales staff failed to achieve last month's sales targets when training in the mobile products and supporting sales systems and processes was first started. This month the sales team is working after hours and weekends to try to meet the current targets while developing the new skills needed. It is generally felt that this situation is unsustainable.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?
Which 2 statements represent appropriate entries for the Development
Approach Definition?