FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. APMG-International Certification
  3. AgilePM-Practitioner Exam
  4. APMG-International.AgilePM-Practitioner.v2025-09-09.q58 Dumps
  • ««
  • «
  • …
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • »
Download Now

Question 36

Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?

Correct Answer: D
insert code

Question 37

Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation

Correct Answer:

Explanation:
For each action in Column 1, here is the iterative development activity that the action represents from Column
2:
* The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
* B. Action
* The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
* A. Thought
* Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
* C. Conversation
* The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
* C. Conversation
* The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
* B. Action
insert code

Question 38

Which approach is the MOST likely to ensure that the participants apply themselves productively to the co-design tasks in a workshop?

Correct Answer: D
Comprehensive and Detailed Step-by-Step Explanation:
Facilitating a productive workshop requires careful planning and management of participant interaction and focus. Option D is the most effective approach because it sets the tone for collaboration and alignment early in the workshop.
1. Importance of Establishing Principles for Interaction:
* Establishing basic principles for interaction ensures that participants understand the expectations, goals, and structure of the workshop.
* It helps create a positive environment where participants are encouraged to collaborate, contribute ideas freely, and stay on track.
* This aligns with AgilePM principles, which stress the importance of clear communication, collaboration, and shared understanding.
2. Analysis of the Options:
* Option A: Work through items without any limitations on the solution
* Allowing unlimited exploration may lead to unproductive discussions, scope creep, or a lack of focus. Agile workshops require time-boxing and prioritization to maintain direction and ensure results.
* Option B: Postpone discussion on practical changes until after the workshop has finished
* Deferring discussions on practical implementation undermines the purpose of the workshop, which is to co-design actionable solutions. Agile encourages iterative discussions and addressing practicalities in real-time.
* Option C: Place a time-limited focus onto the delivery of the workshop's outputs
* While time-limiting focus is a good practice, this option overlooks the critical role of setting expectations and fostering collaboration. Without clear principles for interaction, time limits alone may not lead to productive outcomes.
* Option D: Establish and discuss basic principles for interaction at the start of the workshop (Correct Answer)
* Setting ground rules ensures participants remain aligned with the goals and are motivated to contribute productively. It minimizes potential conflicts, distractions, and misaligned expectations, fostering a collaborative atmosphere.
3. Application in UniCo's Scenario:
* In the UniCo case, where integration and cultural shifts are key, establishing principles such as respect for diverse viewpoints (Selco vs. UniCo staff) and focusing on actionable outputs would encourage productive discussions.
* Discussing principles ensures buy-in from participants and helps reduce resistance to change.
4. Agile Practitioner Documentation References:
* Workshops in AgilePM: AgilePM emphasizes creating structured workshops with defined roles, expectations, and interaction principles to maximize productivity.
* Agile Values - Individuals and Interactions: Clear guidelines for collaboration are foundational to achieving meaningful results in workshops.
* Facilitation Techniques: Best practices include setting principles such as time-boxing, respecting all inputs, and focusing on actionable outputs.
References:
* Agile Project Management Handbook, Chapter 7: Facilitation and Workshop Best Practices
* Agile Manifesto Principle: Individuals and Interactions Over Processes and Tools
* Agile Facilitation Guidelines: Establishing Ground Rules for Effective Workshops
insert code

Question 39

The Legal Specialist has reviewed the plans for the rebranding work and has assessed how this will affect current and future contracts. They are now pressing the Change Manager to establish the deadlines and to schedule when their input will be most needed.
Which preference does this behavior BEST display?

Correct Answer: C
Comprehensive and Detailed Explanation:
This question uses the Myers-Briggs Type Indicator (MBTI) framework. The behavior described aligns most closely with the Judging preference, which is associated with organization, structure, and a desire for clear plans and deadlines.
1. Why the Answer is Judging (C):
* The Legal Specialist is focused on establishing deadlines and ensuring their input is scheduled. These traits are characteristic of the Judging preference.
* People with a Judging preference prefer:
* Planning and structure.
* Clarity in schedules and deadlines.
* Order and predictability in tasks.
* Pressing for specific deadlines and schedules reflects a strong inclination toward structured, organized work.
2. Analysis of Other Options:
* Option A: Thinking
* The Thinking preference is about decision-making based on logic and objectivity. While the Legal Specialist's assessment of contract impacts involves analysis, their behavior in this scenario focuses on planning and organization rather than logical evaluation.
* Eliminate.
* Option B: Feeling
* The Feeling preference relates to decision-making based on empathy and values. This behavior is not motivated by emotional considerations or interpersonal dynamics but by a focus on task management and structure.
* Eliminate.
* Option D: Perceiving
* The Perceiving preference is characterized by flexibility, adaptability, and a preference for keeping options open. The Legal Specialist's push for deadlines and structure contrasts with the more fluid, spontaneous approach associated with Perceiving.
* Eliminate.
3. Practical Example of Judging Behavior:
* A Judging individual might request a clear project timeline with milestone dates to ensure they can prioritize their work effectively. They value predictability and dislike ambiguity, which aligns with the described behavior of the Legal Specialist.
4. Reference to MBTI:
* Judging (J):
* Focuses on order, structure, and planned decision-making.
* Prefers defined timelines and organized approaches to work.
* Perceiving (P):
* Prefers flexibility, spontaneity, and keeping options open.
insert code

Question 40

Two Sales staff members appear to have lost energy for the change process and did not attend recent change meetings. When questioned, they said they were so overwhelmed by the number of changes in systems, materials, technical knowledge, and processes that they couldn't deal with any more.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance from staff?

Correct Answer: A,D
Comprehensive and Detailed Step-by-Step Explanation:
1. Analysis of the Scenario: The staff members are experiencing change fatigue due to the overwhelming number of adjustments in systems, processes, and technical knowledge. This fatigue often arises during significant organizational transformations like the one UniCo is undergoing, where staff members feel unprepared or unsupported to handle multiple changes.
Agile Project Management (AgilePM) emphasizes adaptive change management, where incremental changes are planned and staff are supported throughout transitions. The Agile approach also recommends prioritizing manageable changes to prevent burnout.
2. Option Evaluation:
A: Find out which elements could remain unchanged so that future sales are unaffected.
* Explanation: Maintaining some consistency during the change process can help overwhelmed staff feel less stressed. By preserving elements that do not directly need alteration, employees can focus on critical areas that need improvement without feeling they are losing their entire work foundation.
* Reference from AgilePM: Agile emphasizes incremental delivery and the need to protect stability where possible during change efforts. This is key to balancing innovation with operational continuity.
* Why Correct: This approach reduces unnecessary change and helps staff focus on priority areas, reducing resistance and fatigue.
B: Add personal staff targets to ensure that the changes in the sales operations are continued.
* Explanation: While setting targets can be a motivational tool, introducing personal targets during a period of resistance or overwhelm can exacerbate stress and lead to further disengagement.
* Why Incorrect: AgilePM advocates for team empowerment and reducing pressure during resistance phases. Adding personal targets does not address the root cause of change fatigue.
C: Assign the staff members to projects outside of this change, to prevent them undermining the changes needed.
* Explanation: Removing staff from the process entirely may appear to prevent further resistance, but it also excludes them from adapting to and learning the new processes. Such an action can lead to further disengagement and even attrition.
* Why Incorrect: AgilePM encourages collaboration and engagement rather than sidelining staff during organizational changes.
D: Consider limiting the changes to those that are related to each other during each iteration of change in sales.
* Explanation: By grouping related changes, staff can focus on cohesive elements rather than being overwhelmed by disjointed changes. This iterative approach aligns with AgilePM principles, which emphasize breaking down tasks into smaller, manageable chunks.
* Reference from AgilePM: The iterative and incremental approach in Agile ensures that teams manage workload effectively while focusing on high-priority changes.
* Why Correct: Limiting and organizing changes into related areas ensures clarity, reduces cognitive load, and builds confidence among the sales staff.
E: Ensure these staff members are rewarded for raising issues with the implementation.
* Explanation: Rewarding staff for raising concerns is a positive reinforcement tactic. However, it does not address the root issue of change fatigue. While this could encourage openness, it does not reduce the overwhelming workload or clarify processes.
* Why Incorrect: Although AgilePM emphasizes transparency, this approach does not mitigate the resistance caused by change overload.
3. Final Recommendation:
* Correct Actions: A and D effectively address the root causes of resistance (overwhelm and fatigue) by maintaining stability where possible and grouping related changes into iterations.
* These solutions align with AgilePM's focus on iterative change, manageable workloads, and staff engagement.
* Incorrect Actions (B, C, E): These options either fail to address the root problem or risk disengagement further.
References:
* AgilePM Practitioner Guide, Chapter on Stakeholder Engagement and Managing Change.
* AgilePM Principles: Incremental Delivery and Focus on the Business Need.
* Agile Change Management Strategies for Overcoming Resistance.
insert code
  • ««
  • «
  • …
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • »
[×]

Download PDF File

Enter your email address to download APMG-International.AgilePM-Practitioner.v2025-09-09.q58 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.