FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMI-200 Exam
  4. PMI.PMI-200.v2026-01-15.q132 Dumps
  • ««
  • «
  • …
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • …
  • »
  • »»
Download Now

Question 101

An executive sponsor asks a team when a specific feature will be ready for release. A team member states the feature will be ready by the end of release 3 because it is not a core feature. The team member directs the sponsor to an information radiator, where the sponsor sees several notes grouped by release numbers and posted on the wall.
What is the sponsor looking at?

Correct Answer: D
The sponsor is looking at the product roadmap, which is a visual representation of the product's planned features and their expected delivery timelines across multiple releases. It typically shows the major milestones, planned releases, and features grouped by their respective release numbers. This aligns with the sponsor's inquiry about when a specific feature will be ready, as the roadmap provides a high-level view of the product's development and release schedule.
insert code

Question 102

At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient. What should the project team have done prior to product release?

Correct Answer: A
insert code

Question 103

A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.
What should the team lead do next?

Correct Answer: A
The team lead should work to resolve the conflict by negotiating with the project director. Since the lead developer cannot complete their work due to the request for a detailed testing plan, the team lead should seek to limit the scope of the documentation request. By negotiating for fewer details or a reduced scope of testing documentation, the team can continue their work on the iteration while still meeting the project director's needs. This approach balances the need to progress with development and address the request without causing significant delays.
insert code

Question 104

A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.
What should the servant leader do?

Correct Answer: A
As a servant leader, it is important to address the root cause of the disruption, which in this case is the director's repeated visits and distracting conversations. Coaching the company director on agile practices and good communication helps them understand the need to minimize interruptions and foster a productive environment for the team. This approach will help align the director's behavior with Agile principles, ensuring that the team can focus on delivering value without unnecessary distractions. By educating the director, the servant leader can improve overall team dynamics and project efficiency.
insert code

Question 105

On what should an agile team work to achieve predictable flow?

Correct Answer: A
insert code
  • ««
  • «
  • …
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMI-200.v2026-01-15.q132 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.