FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP-CN Exam
  4. PMI.PMP-CN.v2024-04-19.q212 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 1

一家公司剛開始使用敏捷方法管理專案。由於這一變化,總經理擔心即將進行的專案的範圍定義過程。
專案經理應該怎麼做才能確保專案範圍完全定義?

Correct Answer: B
Explanation
The project manager should help the sponsors and stakeholders create a clear and shared product vision that describes the purpose, features, and benefits of the product. The product vision guides the project scope and provides a common understanding of what the project aims to deliver. The project manager should also facilitate collaboration and communication between the team and the product owner, who is responsible fordefining and prioritizing the product requirements. The team and the product owner should work together to refine and validate the requirements throughout the project, using feedback loops and iterative delivery. This way, the project scope is continuously aligned with the customer needs and expectations, and any changes or uncertainties are managed effectively. References: (Project Management Professional (PMP) Reference Materials source and documents) A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter
2: Value Delivery System, Section 2.3.1: Agile Principles and Values
Agile Practice Guide, Chapter 3: Life Cycle Selection, Section 3.1: Introduction to Life Cycles
[PMP Exam Content Outline], Domain II: Process, Task 2: Determine project scope.
insert code

Question 2

在專案的早期階段,需求文件未獲得批准。經查明,用戶方的領導者未包含在任何要求收集通信中。
哪些檔案可能遺失或過時?

Correct Answer: A
Explanation
The stakeholder register is a document that identifies and analyzes the project stakeholders, their roles, interests, expectations, influence, and communication requirements1. It is an output of the identify stakeholders process, which is performed during the early phase of a project2. If the leader of a user party was not included in any of the requirements collection communications, it means that the stakeholder register was likely missed or outdated, and the stakeholder analysis was not performed properly. This could lead to unmet stakeholder needs, conflicts, delays, or rework3. References:
1: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter 13, Section 13.1.3.1
2: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter 13, Section 13.1.1
3: A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter 13, Section 13.1.2
insert code

Question 3

在專案的執行階段,客戶的利害關係人之一每週都會要求更改範圍。專案經理應該採取哪三項行動來解決這個問題?
(選三項)

Correct Answer: C,D,E
Explanation
According to the PMBOK Guide, scope changes are inevitable in most projects, and they can have positive or negative effects on the project objectives. Scope changes can be initiated by various sources, such as stakeholders, customers, sponsors, team members, or external factors. Scope changes should be managed through a formal change control process, which involves identifying, analyzing, approving, and implementing the changes. The change control process should be aligned with the project management plan, which defines how changes will be monitored and controlled throughout the project life cycle. The project management plan also includes the scope management plan and the scope baseline, which describe how the project scope will be defined, validated, and controlled.
In this question, the project manager is facing a situation where one of the customer's stakeholders keeps requesting changes to the scope every week during the execution phase of the project. This can create challenges for the project manager and the project team, such as increased costs, delays, rework, scope creep, quality issues, or stakeholder dissatisfaction. To resolve this issue, the project manager should take the following three actions:
Highlight the impacts of the changes during the next project meeting. The project manager should communicate with the customer and the project team about the scope changes and their implications for the project. The project manager should explain how the changes will affect the project scope, schedule, cost, quality, resources, risks, and benefits. The project manager should also present the alternatives and trade-offs for each change, and seek feedback and input from the stakeholders. This will help to create a shared understanding of the situation, and to facilitate the decision-making process.
Schedule a meeting with the customer to align the approach. The project manager should meet with the customer and the stakeholder who is requesting the changes, and discuss the reasons and expectations behind the changes. The project manager should also review the project scope statement, the scope baseline, and the change control process with the customer, and clarify the roles and responsibilities of each party. The project manager should also negotiate with the customer and the stakeholder to prioritize the changes, and to agree on the criteria and process for approving and implementing them.
This will help to establish a common vision and a collaborative relationship with the customer, and to manage their expectations and satisfaction.
Update the relevant project documents with this obstacle. The project manager should document the scope changes and their impacts, and update the relevant project documents accordingly. The project manager should also record the issue of frequent scope changes, and the actions taken to resolve it, in the issue log. The project manager should also update the risk register, the stakeholder register, the lessons learned register, and any other project documents that may be affected by the scope changes.
This will help to maintain the accuracy and consistency of the project information, and to support the project monitoring and controlling activities.
The other options are not correct because they do not provide a valid way to resolve the issue of frequent scope changes. Option A is wrong because it suggests that the project manager should adjust the project management plan to include the changes in scope, without following the change control process or assessing the impacts of the changes. This would violate the project management plan and the scope baseline, and could lead to scope creep, cost overruns, schedule delays, or quality problems. Option B is wrong because it implies that the project manager should continue the execution as planned and defer the changes to a future phase, without communicating with the customer orthe stakeholder who is requesting the changes. This would ignore the customer's needs and expectations, and could result in dissatisfaction, conflict, or rejection of the project deliverables. References:
PMBOK Guide, 6th edition, pages 134-135, 154-155, 161-162
How to Manage Scope Changes on a Project
Scope Change Management - Project Management Knowledge
Scope Change Control - Project Management Institute
insert code

Question 4

在敏捷團隊回顧期間,專案團隊成員提到程式碼品質正在下降,這可能會導致未來的返工隨著時間的推移變得難以管理。專案經理該做什麼?

Correct Answer: B
Explanation
According to the Agile Alliance1, the definition of done (DoD) is a set of criteria that a product increment must meet for the team to consider it complete and ready for customers. It is a shared understanding among the team members of when a product increment is ready for release, even when the increment is large and consists of many items. By clearly defining what "done" means to the project, an agile team can focus on delivering value with every sprint and minimizing rework. It is important to note that one person does not create the Definition of Done.Instead, it is agreed upon by the entire project team, including developers, testers, product owners, and other stakeholders. This ensures a smoother process during sprints since everyone is using the DoD as a guide alongside any checklists before marking an item as complete.
The PMBOK Guide - Seventh Edition2 also mentions the DoD as a key concept in agile development. It states that the DoD helps to ensure that tasks are thoroughly planned and thought through and that the final product meets the required standards of quality. The PMBOK Guide - Seventh Edition will now be a reference to inform the development of the exam items. However, before any validated exam item is added to the exam, there is a very rigorous and thorough review and field test cycle3.
Therefore, the best option for the project manager to do in this scenario is to help the team create the DoD to improve delivery quality. This will help the team to identify and address the issues that are affecting the code quality and prevent future rework. Comparing the cost of improving quality against the cost of failure and adjusting the budget (option A) may not be feasible or effective in an agile environment, where changes are frequent and unpredictable. Adding testing items to the backlog to assess quality periodically (option C) may not solve the root cause of the problem and may delay the delivery of value to the customers. Expanding the team in order to improve the quality of the project (option D) may not be a viable solution either, as it may introduce communication and coordination challenges and increase the complexity of the project.
References: 1: What is the Definition of Done? Understanding DOD in Agile - Atlassian 2: PMBOK Guide
- Seventh Edition | Project Management Institute 3: PMP Exam Prep | PMI - Project Management Institute
insert code

Question 5

規劃會議後,一個新項目已啟動。該專案受到組織中高階主管的直接監督。審查會議結束後,專案經理無意中聽到一名高階主管要求一名團隊成員提供儀表板以顯示整體專案狀態。
專案經理該做什麼?

Correct Answer: B
Explanation
= The project manager should tell the team member to route the request through the project manager, as this is the best way to ensure that the communication is consistent, accurate, and aligned with the project objectives.
The project manager is responsible for managing the communication with the stakeholders, including the executive, and for providing them with the appropriate level of information. The project manager should also verify the validity and feasibility of the request, and update the communications management plan accordingly. The other options are not the best actions to take in this situation, as they do not follow the established communication protocols or respect the project manager's authority. References: = A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Seventh Edition, Chapter 5: Project Communications, Section 5.2: Manage Communications, Page 137-138.
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMP-CN.v2024-04-19.q212 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2025 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.