FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP-CN Exam
  4. PMI.PMP-CN.v2024-04-19.q212 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 16

一位經驗豐富的專案經理正在處理一個複雜的混合項目,該專案與其他專案有多個依賴關係。專案經理應該如何降低與這些外部依賴相關的風險?

Correct Answer: B
Explanation
According to the PMBOK Guide, a hybrid project is a project that uses a combination of predictive, adaptive, and iterative approaches. A hybrid project may have multiple dependencies with other projects, which can increase the risk of schedule delays, scope changes, or resource conflicts. To reduce this risk, the project manager should assess consolidated project plans for dependencies, gaps, and continued business value. This involves reviewing the project plans of all related projects, identifying any interdependencies or overlaps, and evaluating the alignment of the project objectives and deliverables with the organizational strategy and stakeholder expectations. By doing this, the project manager can ensure that the project is on track, avoid any unnecessary rework or duplication, and optimize the use of resources and time. References:
1: A Guide to the Project Management Body of Knowledge (PMBOK Guide), Seventh Edition, page 21
2: A Guide to the Project Management Body of Knowledge (PMBOK Guide), Seventh Edition, page 47
3: A Guide to the Project Management Body of Knowledge (PMBOK Guide), Seventh Edition, page 49
insert code

Question 17

團隊成員正在與專案經理進行討論。在上次回顧會議中,團隊意識到過時的設備可能會影響專案的下一個迭代。團隊建議購買新設備,因為它對於最終交付成果的成功至關重要。
專案經理接下來該做什麼?

Correct Answer: D
Explanation
The cost management plan is a component of the project management plan that describes how the project costs will be planned, estimated, budgeted, managed, and controlled. It also defines the processes, roles, responsibilities, tools, and techniques for cost management, as well as the thresholds, rules, and procedures for handling changes and variances. Therefore, the project manager should review the cost management plan to determine how to address the issue of obsolete equipment that could affect the next iteration of the project.
The cost management plan can help the project manager to identify the available resources, reserves, and funding options, as well as the steps and criteria for submitting and approving a change request, if needed. The other options are not as appropriate or effective as reviewing the cost management plan, as they may not follow the established guidelines or consider the impact of the issue on the project objectives and constraints.
Checking the project budget to verify if there is enough contingency reserve may not be sufficient or accurate, as the contingency reserve may not cover the cost of buying new equipment, or it may be allocated for other risks or uncertainties. Telling the team members that more equipment is not part of the project's scope may not be realistic or feasible, as the obsolete equipment may compromise the quality, functionality, or value of the final deliverable, or it may cause delays, rework, or defects. Submitting a change request to increase the budget and buy new equipment may not be necessary or justified, as there may be other alternatives or solutions to address the issue, or the change request may not meet the approval criteria or process. References:
PMI, A Guide to the Project Management Body of Knowledge (PMBOK Guide) - Sixth Edition, Project Management Institute Inc., 2017, pp. 235-236, 247-248, 487.
The ABC of obsolescence management, Netilion Blog, 2023, pp. 1-2.
6 Steps to Equipment Obsolescence Management, Tool Tracking Software, 2023, p. 1.
insert code

Question 18

專案正處於最後階段,關鍵利害關係人要求更改產品功能,這將導致關鍵路徑增加 2 週時間。專案經理該做什麼?

Correct Answer: B
Explanation
According to the PMBOK Guide 7th Edition, a change request is any request to modify the agreed-upon project scope, schedule, cost, quality, or other project baselines. A change request can be initiated by any stakeholder at any stage of the project, and it should be evaluated for its impact on the project objectives and constraints. Therefore, the project manager should perform a detailed assessment to analyze the impact of the change request on the product feature, the critical path, and other project aspects, such as risk, quality, and stakeholder satisfaction. This will help the project manager to determine the feasibility, desirability, and priority of the change request, and to propose the best course of action to the change control board. Rejecting the change request, using schedule compression methods, or initiating a risk response strategy are not appropriate actions, as they do not address the root cause of the change request, the needs and expectations of the key stakeholder, or the potential benefits or drawbacks of the change request for the project outcome. References: PMBOK Guide 7th Edition, page 141-142.
insert code

Question 19

由於供應商出現問題,專案團隊遇到了進度延誤的情況。有些任務處於關鍵路徑上。
遇到這種情況,專案經理該怎麼辦?

Correct Answer: B
Explanation
According to the PMBOK Guide, the project manager is responsible for managing the project work and ensuring that the project objectives are met. If there are issues that affect the projectschedule, scope, quality, or cost, the project manager should escalate them to the appropriate level of authority for resolution. In this case, the supplier-related issues are causing schedule delays on the critical path, which means they could jeopardize the project completion date. Therefore, the project manager should escalate them to the sponsor, who is the person or group that provides the financial resources and support for the project. The sponsor can help resolve the issues by negotiating with the suppliers, providing additional resources, or approving changes to the project plan. References: PMBOK Guide, 7th edition, pages 11, 12, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, and 25.
insert code

Question 20

專案經理即將啟動一個大型項目,但要求不明確、期限固定且預算固定。客戶無法提供產品負責人,因為他們沒有足夠的能力,而且他們只想在專案期間參與幾次。
專案經理應該如何規劃和管理專案?

Correct Answer: A
Explanation
In a large-scale project with unclear requirements, a fixed deadline, and a fixed budget, the project manager should adopt an agile approach that allows for flexibility, feedback, and collaboration. The project manager should agree with the client on a minimum viable product (MVP), which is the smallest version of the product that can deliver value to the customer. The project manager should also establish deadlines for review, where the client can provide feedback and prioritize the features for the next iteration. The project manager should run the project with a backlog, which is a list of features and requirements that are prioritized and refined by the team, and weekly sprints, which are short cycles of work where the team delivers a potentially shippable product increment. This way, the project manager can manage the project scope, schedule, and cost effectively, and deliver a product that meets the customer's needs and expectations. Option A is the best answer because it follows the agile principles and practices that are suitable for this type of project. Option B is not a good answer because it shows a lack of professionalism and responsibility from the project manager.
Option C is not a good answer because it may not be feasible or realistic to convince the client to provide a product owner, and it may delay the start of the project. Option D is not a good answer because it follows a traditional approach that is not suitable for this type of project, as it assumes that the requirements are clear and stable, and does not allow for frequent feedback and changes. References: [Agile Practice Guide], pages
14-15, 21, 25-26; [A Guide to the Project Management Body of Knowledge (PMBOK Guide)], Sixth Edition, pages 18-19, 174-175.
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMP-CN.v2024-04-19.q212 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.