FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMP-CN Exam
  4. PMI.PMP-CN.v2024-04-19.q212 Dumps
  • ««
  • «
  • …
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • …
  • »
  • »»
Download Now

Question 26

專案經理注意到一名團隊成員一直在努力完成某些任務,這可能最終會影響完成日期。
團隊士氣低落,因為如果不按時完成就無法獲得預期的獎金。
專案經理接下來該做什麼?

Correct Answer: D
Explanation
According to the PMBOK Guide, a project manager should use interpersonal and team skills to manage team morale and performance. One of the skills is recognition and rewards, which involves acknowledging the team's achievements, providing positive feedback, and offering incentives for meeting or exceeding expectations. Another skill is coaching and mentoring, which involves providing guidance, support, and advice to help the team members improve their skills, overcome challenges, and achieve their goals. By using these skills, the project manager can motivate the team, foster collaboration, and prevent or resolve conflicts. References: PMBOK Guide, 7th edition, page 182-183.
insert code

Question 27

請參閱附件。

敏捷團隊已經確定了該版本的所有功能的規模。使用上表,如果團隊期望每個衝刺 10 個故事點的速度,需要多少個衝刺才能完成此版本?

Correct Answer: A
insert code

Question 28

任命一名專案經理來管理跨越多個國家(包括次區域內不同時區)的基礎設施專案。大多數專案團隊成員可能永遠不會見面,但他們必須合作以確保滿足可交付成果。
專案經理應該如何確保遠距專案團隊成員之間的良好協作?

Correct Answer: C
Explanation
= According to the PMBOK Guide, 7th edition, communication is one of the key enablers of project performance, and it should be planned, managed, and monitored throughout the project life cycle1. For remote project teams, communication is evenmore critical, as they face challenges such as cultural differences, time zone differences, lack of face-to-face interactions, and potential misunderstandings2. Therefore, the project manager should plan a communication method that suits the needs and preferences of the remote project team members, such as email, phone, video conferencing, instant messaging, or collaboration tools3. The project manager should also allow the project team members to virtually interact with each other, to build trust, rapport, and teamwork4. This will help to ensure good collaboration and coordination among the remote project team members, and to achieve the project deliverables. References:
1: PMBOK Guide, 7th edition, Chapter 4: Plan and Manage Communications, p. 69-70
2: PMBOK Guide, 7th edition, Chapter 4: Plan and Manage Communications, p. 72
3: PMBOK Guide, 7th edition, Chapter 4: Plan and Manage Communications, p. 74-75
4: PMBOK Guide, 7th edition, Chapter 4: Plan and Manage Communications, p. 76
insert code

Question 29

敏捷團隊正在集思廣益,並根據嚴重程度對所有風險進行優先級排序。對於已識別的風險,團隊應該採取什麼措施?

Correct Answer: C
insert code

Question 30

項目經理是平衡矩陣項目組織的一部分。項目經理將直接從新的採購部門主管那裡收到所有工作績效更新,而新的採購部門主管沒有時間向項目經理提供信息。
項目經理應該做什麼?

Correct Answer: A
insert code
  • ««
  • «
  • …
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMP-CN.v2024-04-19.q212 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.