FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • ISC
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • ISC
    ISC
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. Peoplecert Certification
  3. MSP-Practitioner Exam
  4. Peoplecert.MSP-Practitioner.v2026-02-09.q69 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 21

Which of following Best defines capital cost?

Correct Answer: D
Capital costs are the costs of fixed assets and other tangible assets that are required for the programme. The MSP Practitioner states: "Cost of fixed assets and other assets that are found under 'Technology' head in blueprint is called Capital cost." This typically includes equipment, buildings, and infrastructure necessary for the programme outputs.
insert code

Question 22

In Managing the Tranches, which role is responsible for preparing for the next tranche?

Correct Answer: C
insert code

Question 23

The CFO has specified the need to calculate the Net Present Value (NPV) to demonstrate the return on investment for the programme. How should the resulting benefit be expressed?

Correct Answer: B
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
In MSP 5th Edition, the 'Justification' and 'Benefits' themes emphasize that benefits must be measurable and expressed in a way that allows for objective assessment of the programme's value. When a CFO requests a Net Present Value (NPV) calculation, they are looking for a financial representation of the programme's worth. NPV is a financial metric used to represent the value of future cash flows in today's terms. Therefore, the benefits feeding into this calculation must be expressed in financial terms.
Option B is the correct answer because "cost savings" are tangible, financial benefits that can be directly used in an NPV calculation. In the context of the UU scenario, HR efficiencies leading to reduced staff costs provide a direct cash-flow impact. While Option C (additional sales) is also financial, it is often more speculative than cost savings. Option D uses a "cash proxy," which is a technique used in MSP to assign a monetary value to non-financial benefits (like customer satisfaction), but since the scenario specifically mentions HR efficiencies and cost-saving metrics are already available, a direct financial measure is preferred for a formal NPV. Option A is incorrect because non-financial measures (like brand reputation) cannot be directly included in an NPV formula without conversion. MSP 5th Edition stresses that the Business Case must be supported by a robust Benefit Realization Plan where financial benefits are clearly quantified to justify the investment.
insert code

Question 24

There is a risk that the utilities market is changing, with green energy solutions becoming more attractive to customers. As UU does not currently offer this type of green energy, the benefits gained from cross-selling electricity and gas to current water customers may be overestimated.
Which activity is relevant in the 'plan' phase of the Plan-Do-Check-Act (PDCA) cycle?

Correct Answer: B
Comprehensive and Detailed 200 to 250 words of Explanation From Exact Extract of project- programme-and-portfolio-management of 5th Edition MSP:
The Plan-Do-Check-Act (PDCA) cycle is applied throughout MSP to ensure continuous improvement and effective risk management. In the context of risk management, the 'Plan' phase involves identifying and assessing risks, understanding the current environment, and designing the appropriate responses. It is the analytical stage where the programme team gathers data to understand the scale and proximity of a threat to the programme's benefits.
In this scenario, the risk is a shift in market preference toward green energy. Option B is the correct activity for the 'Plan' phase because it involves research and analysis. Before a response can be designed (Do), the programme must understand the market trends and the potential impact on the cross-selling benefits.
Analyzing how many customers competitors are gaining through green energy provides the evidence base needed to adjust the Business Case or the Benefit Profiles. In contrast, Option D represents the 'Do' phase (implementing a response), Option A represents the 'Check' phase (monitoring results), and Option C is also a
'Check' or 'Act' activity to verify the effectiveness of a response already taken. For the 'Plan' phase, the focus remains on understanding the uncertainty to enable informed decision-making.
insert code

Question 25

Which of following is not a principal control for managing the tranches?

Correct Answer: B
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download Peoplecert.MSP-Practitioner.v2026-02-09.q69 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.