FreeQAs
 Request Exam  Contact
  • Home
  • View All Exams
  • New QA's
  • Upload
PRACTICE EXAMS:
  • Oracle
  • Fortinet
  • Juniper
  • Microsoft
  • Cisco
  • Citrix
  • CompTIA
  • VMware
  • SAP
  • EMC
  • PMI
  • HP
  • Salesforce
  • Other
  • Oracle
    Oracle
  • Fortinet
    Fortinet
  • Juniper
    Juniper
  • Microsoft
    Microsoft
  • Cisco
    Cisco
  • Citrix
    Citrix
  • CompTIA
    CompTIA
  • VMware
    VMware
  • SAP
    SAP
  • EMC
    EMC
  • PMI
    PMI
  • HP
    HP
  • Salesforce
    Salesforce
  1. Home
  2. PMI Certification
  3. PMI-200 Exam
  4. PMI.PMI-200.v2026-01-15.q132 Dumps
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
Download Now

Question 1

A project sponsor is upset that an enhancement will be unavailable until next year. What should the product owner do?

Correct Answer: B
insert code

Question 2


The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative.
The agile project lead sends the manager the following email with the initiative's current status.
Which summaries are correct and will be presented during the monthly project review? (Refer to the email and exhibits to the Team Manager)

Correct Answer: D
Step 1: Identifying Remaining MVP Story Points
From the backlog, the MVP-related stories that are not started include:
Accessibility - color blind (4 story points)
Increase security (21 story points)
Add AI chatbot (5 story points)
Total remaining MVP story points = 4 + 21 + 5 = 30
Step 2: Projected Sprint Completion
MVP Completion: The risk register mentions a burn reduction for sprints 4-6 due to holiday schedules.
If the burn rate is consistent after sprint 6, the MVP will be completed by sprint 9.
The entire backlog is projected to complete by sprint 16 assuming no further deviations.
insert code

Question 3

An agile practitioner wants to communicate the effect of technical debt on the project What should the practitioner do?

Correct Answer: A
insert code

Question 4

Which of the following is a list of valid Agile project planning practices?

Correct Answer: C
insert code

Question 5

Which three criteria should be looked at when setting iteration length?

Correct Answer: B
insert code
  • «
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • …
  • »
  • »»
[×]

Download PDF File

Enter your email address to download PMI.PMI-200.v2026-01-15.q132 Dumps

Email:

FreeQAs

Our website provides the Largest and the most Latest vendors Certification Exam materials around the world.

Using dumps we provide to Pass the Exam, we has the Valid Dumps with passing guranteed just which you need.

  • DMCA
  • About
  • Contact Us
  • Privacy Policy
  • Terms & Conditions
©2026 FreeQAs

www.freeqas.com materials do not contain actual questions and answers from Cisco's certification exams.